CJ1610Z Gantry moving CNC high speed plate drilling machine operating and maintenance personnel, must go through professional training. At the same time meet the following requirements:
1, familiar with the structure of the CNC plane drilling performance and computer operating procedures. It is forbidden to use their own disk in order to prevent the virus into the computer.
2, operations personnel shall ensure that adequate sleep, will remain focused in step. It is important to pay special attention to the device "danger" and "no" safety signs.
3, should be carefully before starting the inspection on the device key components fastening, can be turned on after confirmed. According to the steps to shut down the computer after work, console, electrical cabinets and total power switch.
4, CJ1610Z Gantry moving CNC high speed plate drilling machine drilling must not use the oil temperature more than 50 ℃, otherwise the system will be damaged.
5, lifting materials and artifacts, forbidden collision this equipment or from the top of the equipment to traffic.
6, CJ1610Z Gantry moving CNC high speed plate drilling machine oil hole slide block and the moving parts, before each run should be clean, reoccupy N46 # machine oil lubrication. Guide rail surface and screw oil once per class, and each class with air gun to blow clean the scrap iron or sliding surface oil dirties.
7, the operator in the machine work, may not be far away from his post. Does leave, should stop, cut off power supply.
8, CNC plane drilling in work or adjust, it is strictly prohibited to clip finger into his mouth and close to the bit.
9, CNC plane drilling adjustment or change the bit must be set when the guardian, to cut off the power supply and remove the key, just in case someone accidentally shut, the key must have a special custody.
10, the operator shall not be adjusted without CJ1610Z Gantry moving CNC high speed plate drilling machine of system pressure, does need must inform repair personnel, must be repaired by the personnel responsible for the adjustment.
11 stop before restarting, equipment, operations personnel must have clear instructions, will cooperate with each other, so as to avoid accidents.
12, power equipment, the reboot the system must perform back in order, confirm the control system to establish the correct initial states of the system.
13, machine backup important parameters (such as the reference point value) must be in a safe place, for later use.
Strictly abide by the CJ1610Z Gantry moving CNC high speed plate drilling machine safety operation procedures, fill in the hand-over records, before coming off work, wipe machine and lubricating maintenance.
cc: Kevin kevin@jntime.com
Address: No. 3999 , Airport Road, Lingang Economic Development Zone, Jinan,Shandong,China
Zip:250107 Fax:0531-8873 5288 Sales Hotline:0531-8873 5188
After-Sales Hotline:136 0641 1517/150 2000 3877/133 0531 7322